Project for the Web Accelerator Integration - Default Field Mappings and Scheduled Strategies

  • Updated

This article describes the default field mappings and scheduled strategies that are set up when the Project for the Web Accelerator integration is installed.

Default Field Mappings

Plans - Projects

OnePlan Fields

Project Fields

Direction

Notes

Name

Name

Both

Required

Timesheet Hours

Effort Completed (Hours)

Project to OnePlan

Start (Summary Task)

Start Date

Project to OnePlan

Due (Summary Task)

Finish Date

Project to OnePlan

% Complete

% Complete

Project to OnePlan

Owner

Owner

Project to OnePlan

Manager

Project Manager

Project to OnePlan

Forecast

Forecast

OnePlan to Project

Actual Cost

Actual Cost

OnePlan to Project

Budget

Budget

OnePlan to Project

Benefits

Benefits

OnePlan to Project

Strategic Alignment

Strategic Alignment (ID)

Project to OnePlan

Needs Staffing

Needs Staffing

Project to OnePlan

Business Unit

Business Unit (ID)

Project to OnePlan

Effort Health

Effort Health (ID)

Project to OnePlan

Financial Health

Financial Health (ID)

Project to OnePlan

Funding Source

Funding Source (ID)

Project to OnePlan

Improve Employee Retention

Improve Employee Retention (ID)

Project to OnePlan

Priority

Priority (ID)

Project to OnePlan

Issue Health

Issue Health (ID)

Project to OnePlan

Lower Cost

Lower Cost (ID)

Project to OnePlan

Overall Health

Overall Health (ID)

Project to OnePlan

Project Type

Project Type (ID)

Project to OnePlan

Risk

Risk (ID)

Project to OnePlan

Stage

Stage (ID)

Project to OnePlan

State

State (ID)

Project to OnePlan

Timesheet Charge

Timesheet Charge (ID)

Project to OnePlan

(Recommended, Temporary) Remove this field mapping

Timesheet Type

Timesheet Type (ID)

Project to OnePlan

(Recommended, Temporary) Remove this field mapping

Schedule Health

Schedule Health

Project to OnePlan

Tasks - Tasks

OnePlan Fields

Project Fields

Direction

Notes

Name

Name

Both

Required

Assigned To

Assigned To

Project to OnePlan

Effort

Effort

Project to OnePlan

Start

Start

Project to OnePlan

Timesheet Hours (Actual Hours)

Effort Completed (Hours)

OnePlan to Project

Due

Finish

Project to OnePlan

% Complete

% Complete

Project to OnePlan

Task Dependencies

Task Dependencies (PFTW)

Project to OnePlan

Task Order (OnePlan System)

Display Sequence

Project to OnePlan

Lookup Tables - Lookup Tables

OnePlan Fields

Project Fields

Direction

Notes

Improve Employee Retention (Plan)

Improve Employee Retention (Project)

Project to OnePlan

Lower Cost (Plan)

Lower Cost (Project)

Project to OnePlan

Business Unit (Plan)

Business Unit (Project Task)

Project to OnePlan

Priority (Plan)

Priority (Project)

Project to OnePlan

Financial Health (Plan)

Financial Health (Project)

Project to OnePlan

Effort Health (Plan)

Effort Health (Project)

Project to OnePlan

Schedule Health (Plan)

Schedule Health (Project)

Project to OnePlan

Issue Health (Plan)

Issue Health (Project)

Project to OnePlan

Funding Source (Plan)

Funding Source (Project)

Project to OnePlan

Project Type (Plan)

Project Type (Project)

Project to OnePlan

Timesheet Charge (Plan)

Timesheet Charge (Project)

Project to OnePlan

(Recommended, Temporary) Remove this field mapping

Timesheet Type (Plan)

Timesheet Type (Project)

Project to OnePlan

(Recommended, Temporary) Remove this field mapping

Stage (Plan)

Stage (Plan)

Project to OnePlan

Overall Health (Plan)

Overall Health (Project)

Project to OnePlan

Risk (Plan)

Risk (Project)

Project to OnePlan

Default Scheduled Jobs

SynchLookups: This strategy will synchronize the choice value options in Project for the Web into the corresponding Choice field options mapped in OnePlan.

OnePlanUpdate: Publishes data from Project for the Web into OnePlan.

OnePlanPublish: Publishes data from OnePlan into Project for the Web.