Microsoft Planner Premium Accelerator Integration - Default Field Mappings and Scheduled Strategies

  • Updated

This article describes the default field mappings and scheduled strategies that are set up when the Microsoft Planner Premium Accelerator integration is installed.

Default Field Mappings

Plans - Projects

OnePlan Fields Project Fields Direction Notes
Name Name Both Required
Timesheet Hours Effort Completed (Hours) Planner to OnePlan  
Start (Summary Task) Start Date Planner to OnePlan  
Due (Summary Task) Finish Date Planner to OnePlan  
% Complete % Complete Planner to OnePlan  
Owner Owner Project to OnePlan  
Manager Project Manager Planner to OnePlan  
Forecast Forecast OnePlan to Project  
Actual Cost Actual Cost Planner to Planner  
Budget Budget OnePlan to Planner  
Benefits Benefits OnePlan to Planner  
Strategic Alignment Strategic Alignment (ID) Project to Planner  
Needs Staffing Needs Staffing Planner to OnePlan  
Business Unit Business Unit (ID) Planner to OnePlan  
Effort Health Effort Health (ID) Planner to OnePlan  
Financial Health Financial Health (ID) Planner to OnePlan  
Funding Source Funding Source (ID) Planner to OnePlan  
Improve Employee Retention Improve Employee Retention (ID) Planner to OnePlan  
Priority Priority (ID) Planner to OnePlan  
Issue Health Issue Health (ID) Planner to OnePlan  
Lower Cost Lower Cost (ID) Planner to OnePlan  
Overall Health Overall Health (ID) Planner to OnePlan  
Project Type Project Type (ID) Planner to OnePlan  
Risk Risk (ID) Planner to OnePlan  
Stage Stage (ID) Planner to OnePlan  
State State (ID) Planner to OnePlan  
Timesheet Charge Timesheet Charge (ID) Planner to OnePlan (Recommended, Temporary) Remove this field mapping
Timesheet Type Timesheet Type (ID) Planner to OnePlan (Recommended, Temporary) Remove this field mapping
Schedule Health Schedule Health Planner to OnePlan  

Tasks - Tasks

OnePlan Fields Project Fields Direction Notes
Name Name Both Required
Assigned To Assigned To Planner to OnePlan  
Effort Effort Planner to OnePlan  
Start Start Planner to OnePlan  
Timesheet Hours (Actual Hours) Effort Completed (Hours) OnePlan to Planner  
Due Finish Planner to OnePlan  
% Complete % Complete Planner to OnePlan  
Task Dependencies Task Dependencies (PFTW) Planner to OnePlan  
Task Order (OnePlan System) Display Sequence Planner to OnePlan  

Lookup Tables - Lookup Tables

OnePlan Fields Project Fields Direction Notes
Improve Employee Retention (Plan) Improve Employee Retention (Project) Planner to OnePlan  
Lower Cost (Plan) Lower Cost (Project) Planner to OnePlan  
Business Unit (Plan) Business Unit (Project Task) Planner to OnePlan  
Priority (Plan) Priority (Project) Planner to OnePlan  
Financial Health (Plan) Financial Health (Project) Planner to OnePlan  
Effort Health (Plan) Effort Health (Project) Planner to OnePlan  
Schedule Health (Plan) Schedule Health (Project) Planner to OnePlan  
Issue Health (Plan) Issue Health (Project) Planner to OnePlan  
Funding Source (Plan) Funding Source (Project) Planner to OnePlan  
Project Type (Plan) Project Type (Project) Planner to OnePlan  
Timesheet Charge (Plan) Timesheet Charge (Project) Planner to OnePlan (Recommended, Temporary) Remove this field mapping
Timesheet Type (Plan) Timesheet Type (Project) Planner to OnePlan (Recommended, Temporary) Remove this field mapping
Stage (Plan) Stage (Plan) Planner to OnePlan  
Overall Health (Plan) Overall Health (Project) Planner to OnePlan  
Risk (Plan) Risk (Project) Planner to OnePlan  

Default Scheduled Jobs

SynchLookups: This strategy will synchronize the choice value options in Microsoft Planner Premium into the corresponding Choice field options mapped in OnePlan.

OnePlanUpdate: Publishes data from Microsoft Planner Premium into OnePlan.

OnePlanPublish: Publishes data from OnePlan into Microsoft Planner Premium.