This article describes the actions that will trigger audit log entries.
The Audit feature allows you to keep track of important usage data on a Plan level, and for individual resources.
The following actions when working in a plan will trigger an audit log entry:
-
Creating a work item
-
Updating a work item
-
Deleting a work item
-
Updating a work item using the REST API
-
Converting a work item into a milestone using the Convert to Milestone function
-
Updating work items using the Gantt
-
Adding a user to a plan Shared With list
-
Updating a user in a plan Shared With list
-
Removing a user from a plan Shared With list
-
Archiving a plan
-
Adding a predecessor to a work item
-
Updating a work items calendar
-
Updating a work item's mode
-
Converting a work item to a milestone
-
Marking a work item as inactive
-
Changing a work item to be manually scheduled
-
Copying and pasting work items
The following actions when working with resources will trigger an audit log entry:
-
User logins
-
Editing users
-
Adding new users
-
Changing a generic resources name
-
Using the import option in the resource planner