How to Use Quick Edit for Work Items in OnePlan

  • Updated

Direct Answer: How to Use Quick Edit for Work Items in OnePlan

To use Quick Edit for a work item in OnePlan, right-click the work item in the Work Plan List and select Quick Edit from the contextual menu. The Quick Edit dialog opens with GeneralResourcesDependenciesNotes, and Files tabs, giving you a fast way to review and update a work item without opening the more detailed Advanced Edit dialog.


What This Article Covers: Quick Edit

This article explains each tab in the Quick Edit dialog for a work item: General, Resources, Dependencies, Notes, and Files. Quick Edit is a lighter-weight alternative to Advanced Edit, intended for fast updates rather than a full, type-by-type breakdown of resource assignments.

What you will accomplish
By the end of this article, you will be able to open Quick Edit for any work item and review or update its general information, resources, dependencies, notes, and files.


Before You Begin: Quick Edit


Why This Matters: Quick Edit

Fast access to common fields

Quick Edit gives you one dialog for the fields you update most often — schedule information, resources, dependencies, notes, and files — without opening the full Advanced Edit dialog.

A Work-only Resources tab

Quick Edit's Resources tab only shows Work type resources assigned to the item. It does not display Material or Cost type resource assignments — use Advanced Edit to see and manage those.


Step-by-Step: Using Quick Edit for Work Items in OnePlan

Task: Open Quick Edit for a Work Item

Next to the desired task, click ☰ > Quick Edit.

Open Task Quick Edit.png

Task: Review General Information

The General tab shows general work item information. You configure this form via the Work Type form configuration. See Configure Work Type Forms for more information.

In this example, the task information is organized into:

  • Task Information — NameHealth StatusCharge TypeStatusPriority, and a Complete checkbox.
  • Task Description — A rich text field for describing the work item.
  • Task Schedule — StartDueDeadline Date, and % Done.
  • Task Effort — EffortTimesheet Hours, and Remaining Effort.
  • Task Financials — Estimated Cost and other financial fields associated with the work item.

Quick General Tab.png

Task: Manage Resources from Quick Edit

Use the Resources tab to see resources assigned to the item, listed with Resource Name and Units columns.

Note: The Resources tab in Quick Edit only shows Work type resources. It does not display Material or Cost type resource assignments. For a full breakdown of resources by type, use How to Use Advanced Edit for Work Items in OnePlan instead of Quick Edit.

Quick Resources Tab.png

Task: Manage Dependencies

Use the Dependencies tab to see a summary of the item's relationships, organized into ParentPredecessors, and Successors sections. Each entry shows the related item's number, name, date, and status.

Quick Dependencies Tab.png

Note: For adding or removing predecessor and successor relationships in detail, see Task Dependencies and How to Use Advanced Edit for Work Items in OnePlan.

Task: Add Notes

Use the Notes tab to add and edit rich text notes on the item as needed, using the formatting toolbar for bold, italic, underline, font size, text color, highlight, and bullet or numbered lists.

Quick Notes Tab.png

Task: Manage Files

Use the Files tab to view and manage files linked to the item. Click the + icon to add a file, then select from the drop-down. Linked files are listed with a Display Name you can click to open them.

Quick Files Tab.png


Frequently Asked Questions: Quick Edit

Q: What is the difference between Quick Edit and Advanced Edit?

A: In OnePlanQuick Edit gives you a faster view of general information, a Work-only Resources tab, a dependency summary, notes, and files. Advanced Edit includes the same general information plus separate Predecessors and Successors tabs, resource assignments broken out by Work, Material, and Cost type, and an Advanced tab with additional scheduling fields.


Q: Can I see Material or Cost resources on the Resources tab in Quick Edit?

A: In OnePlan, no. The Resources tab in Quick Edit only shows Work type resources assigned to the item. Use Advanced Edit to see and manage Material and Cost type resource assignments.


Q: Can I manage predecessor and successor relationships in detail from Quick Edit?

A: In OnePlan, the Dependencies tab in Quick Edit only shows a read-only summary of Parent, Predecessor, and Successor relationships. Use Advanced Edit for separate Predecessors and Successors tabs where you can add or remove relationships.


Q: Which dialog should I use for fast updates during daily plan review?

A: In OnePlan, Quick Edit is designed for fast updates and is generally the better choice for daily plan review. Use Advanced Edit when you need the full detail, including type-specific resource assignments.


Q: Can I manage files linked to a work item from Quick Edit?

A: In OnePlan, yes. Use the Files tab in Quick Edit to view linked files and click the + icon to add new ones.


What to Do Next: Quick Edit

Get the full detail view:

Manage resources:

Continue building your schedule: