This article explains how to split a task into two sub-items in the OnePlan Work Plan.
Note
To split a task, you must sort the WBS column first. Once the tasks are in WBS order, you will be able to split tasks.
-
Ensure the WBS column is in your Work Planner view. Then, click the WBS column header to sort the Work Planner into WBS order.
-
Click on the contextual menu next to the task you want to split. Then select Split Task from the drop-down.
Your original task will become a parent item, and will now have two sub-items. The scheduling engine will retain the original dates and duration from the original task for each sub-item, and evenly split the effort from the original task between the two sub-items.
You can update the Start and Due dates, Effort, Duration, Assigned Resources, Status, etc. for each sub-item. These values will roll up to the parent item and will be accounted for in a linked schedule.
-
Click Save to save the split task in your schedule.