Use the Work Plan Gantt

  • Updated

This article explains how to show the Gantt chart for your plan schedule of tasks. You must first select Show Gantt. Then, you may also select Show Baseline and/or Show Critical Path.

Note

The Gantt control requires start and due/finish dates for tasks in order to properly display the Gantt.

Video Length - 1:15

Show Gantt

Click Options in the Work Plan toolbar, then select Gantt.

When the Gantt is shown, three additional icons show on your header. Click the icons to Zoom In, Zoom Out, Scroll To (which will shift the dates to the selected task), or Zoom Fit.

ac585a5a-6539-42f5-8383-949027d7f6de.png

Show Baseline or Critical Path

EClick the Options menu. Go to Gantt > Show Baseline to show the baseline in the Gantt chart. Go to Gantt > Show Critical Path to show the critical path in the Gantt chart.

  1. Ensure the Gantt is already open.

  2. Click Options in the Work Plan toolbar. Then select Baseline (Gantt), or Critical Path (Gantt).

9ffec996-dcf0-4c7e-adfb-7a9cd90d129f.png