This article explains how to use Activities in the OnePlan work planner.
Open the Activities pane to add multiple activities for a selected task. Activities allow for smaller pieces of work to be tracked, that don't need to be a full task in the plan. This allows agile planning of work within the overall plan/schedule.
Video Length - 3:09
-
Select a task.
-
Click Options in the Work Plan toolbar, then select Activities.
-
The Activities pane opens on the bottom half of the screen.
-
Add a new activity.
-
Type into the Add Activity field, then hit the Enter key.
-
Click the Add icon (+). A new activity card will open in the NOT STARTED lane.
-
-
Right click on the desired activity card. Select Edit task. The Edit task form will open.
-
Update the Edit task form.
-
Name: Enter the name of the activity.
-
Description: Enter a description for the activity.
-
Resources: Select resources to assign to the activity.
-
State: Select the state the activity is in.
-
Right click on the desired activity card. Go to Change column, and select the desired activity status.