This article an overview of the OnePlan Resource Plans. OnePlan has both plan-level and organization-wide resource planning capabilities.
Global Resource Plan
The Global Resource Plan shows all resource allocation across all the plans. This is a useful page for managers to review allocation across multiple plans.
If your organization is using the Negotiations feature, the email notifications contain a link to the Resource Plan page, filtered for that plan’s resources. You can also navigate to the page directly via the Resource Plan icon on the OnePlan navigation menu.
Global Resource Plan Overview Video (03:52)
Plan-Level Resource Plan
The plan-level Resource Plan shows resource allocation for a particular plan.
Plan-Level Resource Plan Overview Video (04:39)
Pre-filters
Select a pre-filter to review desired resource types. Pre-filters are configured by your administrator. Pre-filters can be required or optional. When pre-filters are required, no resources will be displayed in the Global Resource Plan page until a pre-filter is applied.
Resource Type Pre-Filter
You can filter the Global Resource Planner by Resource Type so you can view either individual resource allocations or team allocations.
Important
You can only view Resources or Teams allocations. You cannot view both at the same time.
Resource Manager Pre-Filter
The resource manager pre-filter is a server-side filter that loads resources into the Resource Plan area and/or Resource Center area based on user permissions and Resource Managers admin settings. See How the Resource Manager pre-filter works for more information.
Icon Menu
Icons listed in order from left to right:
| Icon | Name | Description | ||||
|---|---|---|---|---|---|---|
| Cost Types Menu | Toggle between Resource Plan cost types. Cost Types are configured per business use case. These allow for analysis of how resources are initially planned compared to how they are actually assigned and work. | |||||
| Add Booking | Click this icon to launch the booking form. | |||||
| Candidates List | Click the icon to toggle showing the Candidates List on the bottom half of the screen. See How do I use the Resource Pane? for more details. | |||||
| Views | Select the View menu drop down to change views, save views, and delete views. | |||||
| Planning Units Mode Menu | Select Hours, % (Percent), or FTE (Full Time Equivalent). | |||||
| Modify View Menu | Settings in this menu include: | |||||
| Resource Plan Advanced Menu | Options in this menu include: | |||||
| Refresh | Click to update the data in your resource plan. |
Resource Plan Details
The bookings are grouped under each resource. Public rows (if the public/private feature is enabled) show.
The summary rows show the total allocation for each resource. The colors are based on their percentage of availability utilized (how much of their time is taken).
Resource Plan Color Legend:
Green Cell: Less than 100% Availability Used
Light Green Cell: 100% Availability Used
Yellow Cell: Greater than 100% — to — Less than or Equal to 110% Availability Used
Orange Cell: Greater than 110% — to — Less than 120% Availability Used
Red Cell: Greater than 120% Availability Used
Green Tab: Resource requirement 100% fulfilled
Yellow Tab: Resource requirement is greater than 80% – to – less than 100% fulfilled
Orange Tab: Resource requirement is greater than 60% – to – less than 80% fulfilled
Red Tab: Resource requirement less than 60% fulfilled
Resource Plan Details and Candidates List
If you show the Candidates List in the lower half of the screen, each resource’s summary row shows remaining availability. The color legend is the same as noted above. See Resource Plan Candidates List Overview for more information about the candidates list.
Resource Approvals with Negotiations
When the Negotiations feature is enabled, the additional status and approval columns show. See How is resource planning done with the Negotiations feature enabled? for more information about the notifications and approvals with negotiations.
Frequently Asked Questions: Resource Plans
Q: What do I see in the Resource Plan for a private plan I do not have access to in OnePlan? A: In OnePlan, the plan name and additional plan information are hidden, and the Plan ID is displayed in place of the plan name. Existing demand can still be visible so you can plan around it, but you cannot edit or replace it, create new assignments for the plan, or open the plan’s details.
Q: Can I contribute to resource planning for a private plan in OnePlan? A: In OnePlan, yes, if you are included in the plan’s Shared With access. Ask the plan owner to add you. Your normal plan information and planning capabilities then become available based on your permissions.
Q: Do View All Plans or Administrative permissions show private plan details in the Resource Plan in OnePlan? A: Not necessarily. In OnePlan, private plan access takes precedence over general system permissions, so these permissions do not automatically reveal the contents of a private plan.
Q: How can I plan resources on a sensitive plan without exposing its details in OnePlan? A: In OnePlan, if resource planning is required but even limited visibility into the private plan is undesirable, consider using public/private resource plan entries where appropriate.
For more information, see Private Plans in OnePlan - Overview.