Direct Answer: How to Set Up Negotiations in the Resource Plan in OnePlan
To set up negotiations in the Resource Plan in
OnePlan, select the Modify Navigation and App
Settings button, select the pencil icon next to
Resource Plan, and expand the
Negotiation topic heading on the Resource Plan settings
page. Select the Negotiation On checkbox to enable
resource negotiations, then choose a cost type from the Cost
Type drop-down (default All Types, with
options Committed, Scheduled, or
Timesheets). When negotiations are enabled, both the
Plan Owner and the Resource Manager
for each resource must agree on the resource allocation before a
Resource Plan row can change from draft to
proposed to committed. This requires the
Resource Plan app to be installed.
What This Article Covers: Negotiations Setup in the Resource Plan
This article explains how to enable Negotiations for the Resource Plan in OnePlan, select the cost type negotiations apply to, and configure Resource Managers so allocations can be reviewed and approved.
What you will accomplish By the end of this article, you will be able to enable Negotiations, choose the applicable cost type, and set up Resource Managers for your OnePlan environment.
Before You Begin: Setting Up Negotiations in the Resource Plan
Before you begin, make sure you have:
- A OnePlan account with administrator-level access to app settings (Needs SME confirmation: exact permission/role name required)
- The Resource Plan app installed and enabled in your environment
- Departments, Roles, or other resource-level fields already configured on the Fields admin page, if you plan to designate managers by Department or Role
- The Timesheets app installed, if you plan to use Timesheet Manager as the resource manager method
Why This Matters: How Negotiations Work in the Resource Plan
Context: What Negotiations Do in the Resource Plan
Negotiations is an advanced OnePlan
feature. When enabled, both the Plan Owner and the
Resource Manager for each resource must agree on the
resource allocation before a Resource Plan row can change from
draft to proposed to
committed.
Context: How Enabling Negotiations After Initial Setup Affects Existing Data
If Negotiations is enabled after your
OnePlan environment is already in use, previously
entered time data in the Resource Plan does not change
automatically. Time already in proposed status remains
proposed and must now be approved by the Project
Manager and Resource Manager. Time already in
committed status remains committed and does
not require approval, though the Project Manager and
Resource Manager approval icons remain blank for that
data.
Step-by-Step: Setting Up Negotiations in the Resource Plan
Task: Enable Negotiations and Select a Cost Type
Starting from the Resource Plan settings page:
- Select the Modify Navigation and App Settings button on the left side of the page, then select the pencil icon next to Resource Plan.
- Expand the Negotiation topic heading.
- Select the Negotiation On checkbox to enable resource negotiations.
- From the Cost Type drop-down, select the cost type negotiations apply to. The default is All Types; other options include Committed, Scheduled, or Timesheets.
Task: Select a Resource Manager Method
Starting from the Users Admin page:
- Expand the Resource Managers heading.
- Select a Method: No Resource Managers, Department, Role, Manager, Timesheet Manager, or another resource-level field. Timesheet Manager only appears if the Timesheets app has been added.
- If you select Manager or Timesheet Manager, the resource manager is determined automatically from that field’s value on each resource’s form.
- If you select Department or Role, continue to the next task to designate managers and delegates.
- If Negotiations is disabled, select No Resource Managers as the method.
Based on the method selected, the resource manager is the user who reviews and approves resource plan allocations. This applies only when Negotiations is enabled.
Task: Designate Managers and Delegates for Departments or Roles
Starting from the Users Admin page, with Department or Role selected as the resource manager method:
- Open the table listing the configured Departments or Roles. Departments and Roles are configured on the Fields admin page, under the Resource topic heading.
- Designate one manager for each Department or Role.
- Designate one or more delegates for each Department or Role. These are the default delegates; each manager can also change delegates for their assigned groups directly on the Resource Plan page.
Frequently Asked Questions: Negotiations in the Resource Plan
Q: What does enabling Negotiations do in the OnePlan Resource
Plan? A: When Negotiations is enabled in
OnePlan, both the Plan Owner and the
Resource Manager for each resource must agree on the
resource allocation before a Resource Plan row can move from
draft to proposed to
committed.
Q: What Resource Manager methods are available in OnePlan? A: On the Users Admin page, you can select No Resource Managers, Department, Role, Manager, Timesheet Manager (if the Timesheets app is installed), or another available resource-level field as the Method.
Q: What happens to existing Resource Plan data if I enable
Negotiations after initial setup? A: Existing data does not
change automatically. Time already proposed remains
proposed and requires approval from the Project
Manager and Resource Manager, while time
already committed remains committed without
requiring approval, though the approval icons remain blank.
Q: Can a manager change the delegates assigned to their department or role? A: Yes. Each Resource Manager can change the delegates for any department or role group they are designated as manager for, directly on the Resource Plan page.
What to Do Next: Negotiations in the Resource Plan
Get started with related tasks: - How Do I Set Resource Managers - How to Configure Resource Plan Types in OnePlan
Learn about related topics: - How to Configure Advanced Resource Plan Settings in OnePlan
Comments
0 comments
Please sign in to leave a comment.