Update Task Status in the My Work Area of the OnePlan Mobile App

  • Updated

This article explains how to update task status in the My Work area of the OnePlan app.

The My Work feature is designed for Team Members to view and update all work assignments on a single page. The Plan Owner will see the updated values when they look at the plan schedule and elsewhere (reports, etc.).

The work items that appear in My Work are based on the tasks date. My Work only shows work items with dates from past or the next 30 days.

App_MyWork.png

To update the status of a task, select the status button of the desired task. The status menu will open.

App_MyWork_-_UpdateStatusSelect.png
App_MyWork_UpdateStatus.png

Select the desired status. Then touch Apply.

App_MyWork_NewStatus.png

The task status and percent complete is updated.

App_MyWork_StatusUpdated.png

To view the task percent complete, touch the carrot to the right of the desired task.

App_MyWork_viewProgress.png

To mark a Work Item “Complete” select the check box to mark an item as complete. the status will update to Complete.

App_MyWork_TaskCompleted_-_Uncheck.png