Why is Committed Effort not synching from the OnePlan Resource Plan to the Committed Effort field in the project General tab? (Power Apps)

  • Updated

Problem

Cause

Solution

Committed Effort is not syncing from the OnePlan Resource Plan to the Committed Effort field in the project General tab.

Committed Effort and Percent Complete fields are using incorrect data types (whole numbers).

Create new fields that use the correct data type (decimal).

  1. Create new Percent Complete and Committed Effort fields as decimals.

  2. Add the new fields to the Form.

  3. Run the OnePlan to PowerApps sync operation to refresh the data.

Was this article helpful?

0 out of 0 found this helpful

Have more questions? Submit a request