Work Plan Troubleshooting

  • Why is my work plan locked?

    Problem I am trying to edit my project work plan, but I cannot change any values.   Cause  The work plan will be locked while it is being edited. If another person tries to edit the same plan at the same time, it be view...

  • Why is my Plan Start Date not aligned with my Work Plan Start Date?

    Problem My Plan Start Date is not aligned with my Work Plan Start Date.  Cause It is most likely you have Constraints on some of your tasks. Solution Add the Constraint Type as a Column and change the Constraint to None. ...